Towing of rig

When a drilling rig was going into a dry dock, the challenge was to secure both the dock and drilling rig against damage as the space was very narrow. As the rig was already on its way to the dock, it was a requirement that the process was ultra short, which made the calculations and the design being done in the mattter of  three days. The work was carried out in cooperation with Lindø port of Odense, Fayard and Maersk.

Our solution

  1. Calculation
  2. Design
  3. Support
"It is a pleasure to see the projects, when they successfully become a reality." Patrick Falk Nybroe Stress Engineer/Flindt Kristensen