flindtkristensen_logo_web_test-removebg-preview.png

Towing of rig | Fayard

Customer:
Fayard

Type:
Maritime

Location:
Denmark

Da en borerig skulle i tørdok, var udfordringen at sikre at både dok og rig imod skader da pladsen var meget snæver. Da riggen allerede var på vej til dokken var det et krav at processen var ultra kort, derfor blev beregninger og design udført på 3 dage. Arbejdet blev udført i samarbejde med Lindø port of Odense, Fayard og Maersk.

Our solution

  1. Calculation
  2. Design
  3. Support
"It is a pleasure to see the projects, when they successfully become a reality."
Patrick Falk Nybroe
Stress Engineer / Flindt Kristensen

Universal storage bridge for Siemens WindPower

Customer:
Siemens Wind Power

Type:
Wind

Location:
Denmark & England

Siemens Wind Power had developed a concept for the universal assembly of a tool for use at offshore parks throughout the world, but needed a maturing and certification of the concept in a very short time – the product was developed and certified by DNV-GL in 10 weeks.

Our solution

  1. Maturation and development of concept
  2. Calculation and analysis
  3. Test